Baadband and quality management
QC & QA
In order to achieve the highest quality objectives and coordinate quality control unit with the latest standards, BABBAND Company has achieved the principles of quality management at the top of its programs. Therefore, the first action of this unit for each project is to provide a quality design in accordance with its type, based on QC and QA standards, through the provision of documents including forms and collected information.
Quality design is the main document for QC and QA and includes the following:
QC Plan
Inspection Instructions
Coordination process between QC and QA departments with other sectors
Controlling documents as attachment in the final project file
Related forms such as inspection report, rent form, confirmation form
Inspection items according to technical specifications
Materials purchasing
Confirmation of Machine Performance
Quality assurance methods
QC and QA unit services include:
Providing data documentation
Preparing and setting up inspection instructions while researching to achieve the latest standards
Preparing and arranging documentation forms as attachment to the final project file
Define coordination process between QC sections with other sections
Training, exchanging and harmonizing information between QC and other departments
Level Certification and personnel competence and preparation the required WPQ and Welders Badges
Determine the items and inspection stations according to the technical specifications of work
Determine inspection methods
Stopping point: control activities parts that should be performed in the presence of inspector are Stopping Points. In such parts without inspector presence, inspection, or any other activity will not be continued.
Spot Check: In these cases, staff or QC and QA inspectors can randomly check the process. Operation in such cases is continuous and will not be stopped for inspection.
Document Verification: Sometimes, inspectors should check documentation that provided by manufacturer QC and QA departments , component manufacturer or contractor. Inspectors can review Manufacturing or services as a Spot Check , certify and sign the required certification.
Final File: purpose of collecting documents and finalizing a file is to provide a complete set of documents that related to Projects inspection & equipment inspection, approved quality plan (QP) and other documents and certifications.
Purchased material control:
Controlling submitted materials with the required material list
Checking the sent material with standards
Collecting all data and certificates that related to materials
Preparing receiving material report
Issuing material inspection request form for project monitoring department and receiveing approval
Confirmation of machinery performance
Equipment calibration
Control the production process when material transfer to the production line:
Materials transfer to fragmentation unit:
Checking and controlling the transferred material with issued required material list
Control changes made during material storage time
Controlling carving of documentary code on sheets that issued from storage department
Verification, marking and ready for transfer to the next unit
Fragmentation, Cutting and punching:
Checking and controlling the cutting order with the desired material
Inspection and controlling the cutted pieces
Controlling on carving of documentary code and relevant information
Checking the inspection request form
Confirmation of transfer material to production line
Inspecting and controlling material before and after drilling on sheets
Check the inspection application form and verification it in order to transfer materials to another sections
Welding:
NDT Inspection: Perform non-destructive testing (PT, MT, UT, RT) according to the reporting procedure
Before welding: instructions application controlling, Pre-heat controlling and edges preparation controlling
During welding: inter-path control and temperature control
After welding: weld appearance control, weld dimensions controlling
Preparation, setting up and welding instructions testing (WPS & PQR) and documents preparation for company projects
studying welding plans and their technical specifications
Check and control the purchase order to being sure about mentioning all required welding materials in purchase order
Check and control the received welding materials according to the purchase order
Observing non-destructive tests to identify defects and provide solutions
Controlling How to store the electrode, powder, welding wire and other welding consumables
Checking application procedure of approved WPS in projects and providing suitable solutions for the best execution of welding instructions (WPS)
Selecting a pilot sample and evaluating the test report and maintaining the records
Preparing NDT MAP Inspection Instructions
Preparing Welding Map
Preparation of related procedures and instructions
Preparing Quality control inspection plan projects ITP and QCP
Meet NCRs from QCs and provide solutions to minimize them and provide relevant statistics
Evaluating the results of destructive and non-destructive tests
Presenting solutions to welders and implementing them to improve quality and quantity
Periodic meetings with welders in order to study common welding defects and their subsequent training, and monthly welders' schedule, including number of correct welds and repairs
Sandblast and color:
Checking and controlling and blasted parts according to data and standards
Controlling and inspecting of assembled accessories
Check the application form for inspection of parts
Parts Verification for final preparation
Preparing invitations to project's monitoring unit in order to parts inspection
Receiving the confirmation from project supervision department to transfer parts to sandblast-paint unit
Invitation letter for project supervision unit:
Receiving confirmation from project monitoring unit for processes correct execution
Issuing Certificates and compliance with inspection forms
Investigate and controlling changes made to piece (damage) at loading time
These documents may also include instructions and procedures for performing project and tracking methods for materials, equipment, or executed operations. In this system, employer could be sure about materials quality and the procedure control.
Documents Review
Setting Final Project File:
Approved results of chemical analysis reports and required physical tests
Weekly and monthly reports
Reporting equipment performance from Workers In Charges
Certification of machinery for regular performance and adjustment
Lacks and performance incompatibility with technical specifications and preparing result report of engineering department
Certified purchased material
Results of confirmed reports of mechanical properties and laboratory reports
Licensing clearance and meeting minutes
Communication and coordination: Communication and coordination between the various procedure stages of QC and QA are shown in following diagram: